PRECOMMISSIONING

Pre-commissioning activities are the non-operating work responsibilities such as adjustments, cold alignment checks, etc. performed by the contractor prior to ready for commissioning or mechanical completion.


READY FOR COMMISSIONING

Occurs when the plant or any part of the plant has been erected in accordance with drawings and specifications and the pre-commissioning activities have been completed to the extent necessary to permit commissioning activities to begin.


MECHANICAL COMPLETION

Occurs when the plant or any part of the plant has been erected in accordance with drawings, specifications and applicable codes and the pre-commissioning activities have been completed to the extent necessary to permit the client to accept the plant and begin commissioning activities. The terms ready for commissioning and mechanical completion are often synonymous.


WATER TRIALS

are commissioning activities conducted to allow run-in and operational testing of the equipment as well as provide operator training and familiarisation.


INITIAL START UP

Occurs when feedstocks are introduced to the plant for the express purpose of producing a product for the first time.


INITIAL OPERATIONS

used to describe the entire process of pre-commissioning, commissioning, initial start up, steady production and performance testing of a plant.